Measure R: Change Order 2A - HVAC in the Common Areas at Bagby, Farnham, and Sartorette |
|
|
District Priorities:
|
|
Enclosure:
|
|
File Attachment:
|
|
Summary:
|
In accordance with the District's change order approval process, the following change order is in connection with the replacement of the HVAC equipment in common areas (e.g., offices, libraries, multi-use buildings, etc.) located at Bagby, Farnham, and Sartorette.
The total change orders for larger modernization projects typically range from 6% - 8%. The attached change order totals $26,652.00 which represents a -3.10% change of the total contracts listed of $859,949.00
1A: Beals Martin and Associates, Inc. Credit of $26,652.00 |
|
|
Funding:
|
|
Recommendation
|
Staff recommends that the Governing Board ratify the one (1) necessary change order; 2A in connection with the HVAC projects in the Common Area at Bagby, Farnham, and Sartorette. |
|
|
Approvals:
|
Recommended By: |
Signed By: |
 |
Carlena Grandey - Administrative Assistant to the Superintendent |
|
Signed By: |
|