Agenda Item
Meeting Date:
9/21/2023 - 7:00 PM  
Category:
Information and Study Items  
Type:
Action  
Subject:
Measure R: Change Orders 1A, 1B, and 1D - Modular Classroom Projects  
District Priorities:
 
Enclosure:
 
File Attachment:
CSD Modular CRs - Galeb Paving CO #1A 09.21.23.pdf
CSD Modular CRs - MK Pipelines CO #1B 09.21.23.pdf
CSD Modular CRs - Cupertino Electric CO #1D 09.21.23.pdf
CSD Modular CRs - Galeb Paving CO #1A 09.21.23 revised.pdf
 
Summary:
In accordance with the District's change order approval process, the following change orders are in connection with the replacement the oldest portables located at Fammatre, Farnham, Sartorette, and Price Middle School.

The total change orders for larger modernization projects typically range from 6% - 8%. The attached change orders total $131,327.25 which represents a 1.83% change of the total contracts listed of $7,183,487.00.

1A: Galeb Paving, Inc. $67,627.87
1B: MK Pipelines, Inc. $12,990.38
1D: Cupertino Electric, Inc. $50,709.00
 
Funding:
 
Recommendation
Staff recommends that the Governing Board ratify the three (3) necessary change orders, 1A, 1B, and 1D, in connection with the Modular Classroom Projects.  
Approvals:
Recommended By:
Signed By:
Carlena Grandey - Administrative Assistant to the Superintendent
Signed By:  
Kristi Schwiebert - Superintendent