Agenda Item
Meeting Date:
11/3/2022 - 7:00 PM  
Category:
Information and Study Items  
Type:
Action  
Subject:
Measure R: Change Orders 3H, 7A, and 7E - Phase 1 Modernization Projects  
District Priorities:
 
Enclosure:
 
File Attachment:
CSD Ph1 Mods - BMI CO #7A 11.03.22 (1).pdf
CSD Ph1 Mods - BMI CO #7E 11.03.22 (1).pdf
CSD Ph1 Mods - OCM CO #3H 11.03.22 (1).pdf
 
Summary:
In accordance with the District's change order approval process, the following change orders are in connection with the Phase 1 Modernization Project to replace the aging HVAC systems at Bagby, Fammatre, Farnham, Sartorette, and Price Middle School.

The total change orders for larger modernization projects typically range from 6% - 8%. The attached change orders total $204,277 which represents a 3.91% change of the total contracts listed of $5,219,800.

3H: O.C. McDonald Co. Inc. (Farnham & Sartorette) $90,270
7A: Beals Martin and Associates, Inc. (Bagby, Fammatre, & Price) $96,047
7E: Beals Martin and Associates, Inc. (Farnham & Sartorette) $17,960
 
Funding:
 
Recommendation
Staff recommends the Governing Board to ratify the three (3) necessary change orders 3H, 7A, and 7E, in connection with the Phase 1 Modernization Projects.  
Approvals:
Recommended By:
Signed By:
Carlena Grandey - Administrative Assistant to the Superintendent
Signed By:  
Kristi Schwiebert - Superintendent