Subject: Measure R: Change Orders 1A, 1B, and 1D - Modular Classroom Projects
District Priorities:
Enclosure
File Attachment:
CSD Modular CRs - Galeb Paving CO #1A 09.21.23.pdf
CSD Modular CRs - MK Pipelines CO #1B 09.21.23.pdf
CSD Modular CRs - Cupertino Electric CO #1D 09.21.23.pdf
CSD Modular CRs - Galeb Paving CO #1A 09.21.23 revised.pdf
Summary: In accordance with the District's change order approval process, the following change orders are in connection with the replacement the oldest portables located at Fammatre, Farnham, Sartorette, and Price Middle School.

The total change orders for larger modernization projects typically range from 6% - 8%. The attached change orders total $131,327.25 which represents a 1.83% change of the total contracts listed of $7,183,487.00.

1A: Galeb Paving, Inc. $67,627.87
1B: MK Pipelines, Inc. $12,990.38
1D: Cupertino Electric, Inc. $50,709.00
Funding:
Recommendation: Staff recommends that the Governing Board ratify the three (3) necessary change orders, 1A, 1B, and 1D, in connection with the Modular Classroom Projects.