Meeting Date:
|
2/6/2025 - 7:00 PM
|
Category:
|
Information and Study Items
|
Type:
|
Action
|
Subject:
|
Measure R: Change Orders 2A and 2D - HVAC in the Common Areas at Fammatre and Price
|
District Priorities:
|
|
Enclosure
|
|
File Attachment:
|
|
Summary:
|
In accordance with the District's change order approval process, the following change orders are in connection with the replacement of the HVAC equipment in common areas (e.g., offices, libraries, multi-use buildings, etc.) located at Fammatre and Price Middle School.
The total change orders for larger modernization projects typically range from 6% - 8%. The attached change orders total $66,451.00 which represents a 3.55% change of the total contracts listed of $1,872,742.00
2A:Beals Martin and Associates, Inc. $65,555.00
2D: Foothill Air Conditioning & Heating, Inc. $896.00
|
Funding:
|
|
Recommendation:
|
Staff recommends that the Governing Board ratify the two (2) necessary change orders; 2A and 2D, in connection with the HVAC projects in the Common Area at Fammatre and Price.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Carlena Grandey - Administrative Assistant to the Superintendent
|
|
Signed By:
|
|
Kristi Schwiebert - Superintendent
|
|
|
|
|
|
|
|